Home arrow About the project arrow Construction arrow Construction schedule
Construction Planning
1st trimester 2008
  • Accommodation compound of 2500 beds
  • Major excavation in Vavouto and the massif for a total of 7 million m3
  • Construction of the port
2nd trimester 2008
  • Dredging of access fairway to port (4.5km, 9 million m3)
  • Commissioning of structural steels
  • Effective commencement of construction of port
  • Construction of modules for the metallurgical plant (probably in Asia)
  • Construction of fluidised bed boilers and steam turbines for the thermal plant
  • Construction of mining infrastructure on the massif
  • Construction of cement foundations
To be concluded in 2009
  • The construction camp
  • Fairway and wharf
To be carried out in 2009
  • Construction of diesel combustion turbines on the Vavouto site
  • Construction of mineral conveyor
  • Construction of primary infrastructures for the Site Industriel Vavouto (SIV) and the Site Industriel Minier (SIM)
  • Arrival by boat of industrial modules
To be carried out in 2010
  • Foundation of modules for the metallurgical plant
  • Survey of exploitation and metal cleaning
  • Electrical and mechanical construction of the thermal plant
Supplying of the first metallurgical furnace: 2011
Production at full capacity: 2013
 